6. Build the Apron and DrainMIXTURE
FOR APRON AND DRAIN
- - 1 Part Cement
- 4 Parts Sand
- 4 Parts Quarry Stone
-
When forming and troweling the apron and drain, be sure they are shaped so
water flows away from the well. The apron extends 1 meter beyond edge of well.

Form the apron and drain and pour concrete. RESERVE A FULL DAY FOR THE
CONSTRUCTION OF THE APRON. Do NOT use bricks in the surface.
- SANDY SOILS
In most of the times, sandy soils do not make good well pits. It
collapses. To avoid this, we use concrete rings that hold the soil from collapsing.
- MAKING CONCRETE RINGS
A ratio of 1:6 is the best mixture of concrete. Make sure you use river
sand of very good quality. Place 6mm wire about 3-4" of the concrete and
another wire about 3-4" above the bottom one. Leave the rings to cure for seven
days.
- PLEASE NOTE: water the rings three times a day.